Gantt charts are not the enemy — bad dependencies are
Finish-to-start everywhere is why your schedule collapses. Here is how to model dependencies you can actually maintain.
The standard objection to Gantt charts is that they are obsolete waterfall artefacts that fall apart on contact with reality. What actually falls apart is a schedule where every task is chained finish-to-start to the one before it. That is not planning, it is a queue with dates attached.
The four dependency types, and when each is correct
- Finish to start (FS). B cannot start until A finishes. Correct when there is a genuine hand-off: you cannot pour foundations before the excavation is done. Overused everywhere else.
- Start to start (SS). B cannot start until A starts. This is the one most teams need and never use. Copywriting and design can run together; they just cannot begin before the brief is signed off. SS with a lag of two days models real parallel work.
- Finish to finish (FF). B cannot finish until A finishes. Ideal for QA trailing development, or documentation trailing a feature.
- Start to finish (SF). Rare and usually a modelling mistake. Legitimate for shift handovers. If you reach for it, check whether you actually mean FS reversed.
Lag and lead are not cheating
A three-day lag on an FS link ("concrete cures") is real information. Teams instead insert a fake task called "wait for curing", which pollutes throughput metrics and assigns a human to waiting. Use lag.
Stop modelling resource contention as a dependency
The most common bad link: "B depends on A because Sarah does both." That is not a logical dependency, it is a capacity constraint. Model it in the workload view, not the schedule. If you encode it as a dependency and Sarah goes on holiday, your whole chain shifts for a reason that no longer exists — and nobody remembers why the link is there.
The critical path is a question, not an answer
The longest chain of dependent work tells you where a one-day slip becomes a one-day slip to the deadline. Everything off the path has float. The useful move is not to stare at the path but to ask: can I break a link on it? Converting one FS link to SS with lag on the critical path shortens the project more than any amount of pressure on the team.
A schedule you can maintain
Three rules. First, no dependency without a stated reason — if you cannot say why in one sentence, delete it. Second, prefer SS and FF for work that overlaps in reality. Third, keep the dependency graph shallow: milestones as anchors, dependencies within a phase, not a 200-link chain from kickoff to launch. Then when a date moves, the chart shifts what genuinely has to shift, which is the entire reason to have one.